Measuring Progress for Construction Projects

construction projects

Why is it important to track progress on construction projects? One very important reason is to prove to investors, stakeholders, and other important sources of support that you’re making progress. And you’ve got the numbers to prove it.

Another reason is to provide reinforcement to the troops. Your workers will see through false encouragement, but when you provide them with the metrics proving they’re doing a good job – and making progress – it’s the best motivator you have.

Tracking Methodologies for Construction Projects

Key metrics for construction projects are:

  • Compliance
  • Deliverables
  • Milestones
  • Spending

Too often, we emphasize the required tasks without analyzing the results. “…Teams are watching the wrong signs and metrics. Instead of leading indicators, which might warn of problems before they happen, these teams may focus on lagging indicators…flagging issues when it’s too late,” says process improvement professional Lori Benson.

Measuring Metrics for Construction Projects

Here are some types of metrics used for construction projects:

  • Cost ratio – This measurement is based on the dollars budgeted vs. labor hours. Example: The overall progress of the project was 42%. The contractor earned 42% of the overhead and fees.
  • Experience/opinion – This method is obviously subjective and not recommended; it can cause conflict between project managers, owners, contractors, or architects.
  • Incremental milestones – Aka the “steps” method for subtasks that need to be completed in a certain order. You calculate each step and the amount of time needed to complete each step. Each completion is an incremental milestone.
  • Start/finish – This is good for short-time tasks. Examples: load testing, flushing/cleaning, pipes. You measure the percentage of completion. Some teams use these length-of-time milestone metrics:
    • 0/100
    • 20/80
    • 50/50
  • Units completed – This is great for task-tracking, especially repetitive jobs. Example: We have 100 light fixtures. Each light fixture takes the same amount of installation time. Units to measure: 100.
  • Weighted/equivalent units – This requires more effort but gets the thumbs-up from many construction projects. Tasks’ measurements are calculated and divided into sub-tasks and their varying units of measurement.

We’re curious to know which progress measurements you use for construction projects.

Construction Monitor is interested in the most up-to-date methodologies for construction projects. Call 800-925-6085 or contact Construction Monitor for data that drives business development.

1 thought on “Measuring Progress for Construction Projects”

  1. This blog is really informative and enlightening. It reminded me of viAct AI EHS Software powered with AI video analytics which gives the ability to monitor construction projects in real-time, identify and resolve issues quickly, and improve communication between team members. Construction Project Management software is essential as it helps to identify potential hazards, track project progress, and verify that work is being completed according to the project schedule. To improve safety and efficiency at project sites, construction management software is a must.

Leave a Comment

Your email address will not be published. Required fields are marked *